Delhi HC ask CIL to supply coal to RPower's Butibori Unit-I

Reliance Power today said state- run Coal India has been directed by the Delhi High Court to immediately commence coal supplies to the Unit-I of Butibori power project.

February 12, 2018 / 17:13 IST
     
     
    26 Aug, 2025 12:21
    Volume
    Todays L/H
    More

    Reliance Power today said state- run Coal India has been directed by the Delhi High Court to immediately commence coal supplies to the Unit-I of Butibori power project.

    "The Delhi High Court in its Order dated January 31, 2018 has granted interim relief to Butibori Thermal Power Plant (TPP) and has directed Coal India Ltd (CIL) to immediately commence the supply of coal to Unit 1 of Butibori Plant, equivalent to Annual Contracted Quantity of 1.23 million tonnes per annum through its subsidiary South Eastern Coalfields Ltd," Reliance Power said in a BSE filing.

    Reliance Power has set up 2 x 300 MW Butibori Plant near Nagpur through its subsidiary Vidarbha Industries Power Ltd (VIPL), which is supplying its entire power to Reliance Infrastructure Ltd (Distribution Utility), which distributes electricity to over 28 lakh consumers in Suburban Mumbai under a long-term Power Purchase Agreement approved by Maharashtra Electricity Regulatory Commission.

    While coal is being supplied to Unit 2 by Coal India through its subsidiary Western Coalfields Ltd, the supply was not commenced to Unit 1 of the Butibori Plant despite a valid Letter of Assurance (LoA) issued by the Coal India subsidiary pursuant to the recommendations of Standing Linkage Committee (Long Term) comprising of Ministry of Coal, Ministry of Power, CIL, Central Electricity Authority and Railways among others, in 2008, the company said.

    The LoA had promised supply of 1.23 million tonnes per annum of coal for Unit 1, it added.

    The coal supply issue was pending for nearly four years after the commissioning of the unit and commencement of power supply to Reliance Infrastructure Ltd in April 2014 under a long-term Power Purchase Agreement approved by Maharashtra Electricity Regulatory Commission.

    The Delhi High Court, has noted that the Butibori Plant has fulfilled the pre-requisite of SHAKTI (Scheme for Harnessing and Allocating Koyala Transparently in India) Policy, wherein Fuel Supply Agreements are to be signed with existing LoA holders, and has a case for having an FSA executed in its favour, it said.

    After the directions of Delhi High Court, both units of Butibori Plant would be getting assured coal supplies from Coal India subsidiaries under 100 per cent FSA/ MoU (fuel supply agreement) and mitigate the uncertainties in supply of 600 MW quality and reliable power to citizens of Mumbai, it added.

    PTI
    first published: Feb 12, 2018 05:02 pm

    Discover the latest Business News, Sensex, and Nifty updates. Obtain Personal Finance insights, tax queries, and expert opinions on Moneycontrol or download the Moneycontrol App to stay updated!

    Subscribe to Tech Newsletters

    • On Saturdays

      Find the best of Al News in one place, specially curated for you every weekend.

    • Daily-Weekdays

      Stay on top of the latest tech trends and biggest startup news.

    Advisory Alert: It has come to our attention that certain individuals are representing themselves as affiliates of Moneycontrol and soliciting funds on the false promise of assured returns on their investments. We wish to reiterate that Moneycontrol does not solicit funds from investors and neither does it promise any assured returns. In case you are approached by anyone making such claims, please write to us at grievanceofficer@nw18.com or call on 02268882347
    CloseOutskill Genai