NHAI turns coronavirus lockdown into opportunity to redress disputes, review projects on war footing

Turning the COVID-19 lockdown into an "opportunity", highways regulator NHAI is working on a war footing to resolve disputes worth a staggering Rs 80,000 crore, besides reviewing projects to expedite work.

April 19, 2020 / 18:09 IST

Turning the COVID-19 lockdown into an "opportunity", highways regulator NHAI is working on a war footing to resolve disputes worth a staggering Rs 80,000 crore, besides reviewing projects to expedite work.

"During this lockdown period, we are holding five to seven video conferences every day to find a resolution to disputes through reconciliation to be ready with all the groundwork.

"Normally what would take months together has been done during the lockdown," NHAI Chairman S S Sandhu, who was on an inspection of the Delhi-Meerut Expressway project when PTI contacted him, said.

Sandhu and other top brass of the National Highways Authority of India (NHAI) have been on an inspection spree of projects, taking the benefit of no traffic on otherwise congested highways.

NHAI, an official said, has at least 180 cases in arbitration involving a sum of about Rs 80,000 crore.

COVID-19 Vaccine

Frequently Asked Questions

View more
How does a vaccine work?

A vaccine works by mimicking a natural infection. A vaccine not only induces immune response to protect people from any future COVID-19 infection, but also helps quickly build herd immunity to put an end to the pandemic. Herd immunity occurs when a sufficient percentage of a population becomes immune to a disease, making the spread of disease from person to person unlikely. The good news is that SARS-CoV-2 virus has been fairly stable, which increases the viability of a vaccine.

How many types of vaccines are there?

There are broadly four types of vaccine — one, a vaccine based on the whole virus (this could be either inactivated, or an attenuated [weakened] virus vaccine); two, a non-replicating viral vector vaccine that uses a benign virus as vector that carries the antigen of SARS-CoV; three, nucleic-acid vaccines that have genetic material like DNA and RNA of antigens like spike protein given to a person, helping human cells decode genetic material and produce the vaccine; and four, protein subunit vaccine wherein the recombinant proteins of SARS-COV-2 along with an adjuvant (booster) is given as a vaccine.

What does it take to develop a vaccine of this kind?

Vaccine development is a long, complex process. Unlike drugs that are given to people with a diseased, vaccines are given to healthy people and also vulnerable sections such as children, pregnant women and the elderly. So rigorous tests are compulsory. History says that the fastest time it took to develop a vaccine is five years, but it usually takes double or sometimes triple that time.

View more
Show

Sandhu told PTI that as a result of intensive meetings, NHAI is in a position to place all matters before the reconciliation committees for speedy disposal of disputes.

"Next week we are likely to take up the matters, work on which have been done, with the conciliation committees for final dispute redressal processes," Sandhu said.

He said the exact number of cases for which work has been done cannot be assessed at the moment as multiple officials are working on different projects and the compilation will be done soon.

Out of the 180 cases involving about Rs 80,000 crore, the officials are currently working on 86 cases worth about Rs 31,000 crore, a source said.

"Work is almost complete on 33 cases with a solid ground ready for disposal of these by the reconciliation committees. These involve a sum of Rs 12,356 crore," the source added.

Work is going on a war footing in other 43 cases involving a sum of Rs 20,000 crore, he added.

The projects under arbitration include Delhi-Agra highway section, Kishangarh-Udaipur road and Chenani-Nashri project, the official said.

The highways builders involved in these projects include ILFS Transportation, Madhucon, Gammon, HCC and Gayatri Projects, among others.

The official said once the conciliation happens, the NHAI payout will be much lesser than the amount projected now as arbitration is a long-drawn process where payout is about 25 per cent but in conciliation, whatever amount is finalised is paid immediately.

Road Transport and Highways Minister Nitin Gadkari has asked the ministry and NHAI officials to convert the coronavirus "crisis into opportunity".

Preparations are afoot to re-start work on highway projects expeditiously in association with the states, while following the guidelines issued by the Ministry of Home Affairs.

Gadkari told PTI: "I have asked NHAI to resolve all cases in three months span."

The NHAI has achieved record 3,979 kms of highways construction in 2019-20.

The feat was achieved on the back of ambitious highways development programmes like Bharatmala Pariyojna.

The construction pace has seen a steady growth, with 3,380 kms construction in FY 2018-19.

Follow our full coverage of the coronavirus pandemic here.

PTI
first published: Apr 19, 2020 06:00 pm

Discover the latest Business News, Sensex, and Nifty updates. Obtain Personal Finance insights, tax queries, and expert opinions on Moneycontrol or download the Moneycontrol App to stay updated!

Subscribe to Tech Newsletters

  • On Saturdays

    Find the best of Al News in one place, specially curated for you every weekend.

  • Daily-Weekdays

    Stay on top of the latest tech trends and biggest startup news.

Advisory Alert: It has come to our attention that certain individuals are representing themselves as affiliates of Moneycontrol and soliciting funds on the false promise of assured returns on their investments. We wish to reiterate that Moneycontrol does not solicit funds from investors and neither does it promise any assured returns. In case you are approached by anyone making such claims, please write to us at grievanceofficer@nw18.com or call on 02268882347