After being given a lifeline, Lavasa applied afresh for environmental clearance to the first phase of its Rs 3000-crore hill city project near Pune, which is being considered by a high-level committee.

February 15, 2011 / 10:08 IST
After being given a lifeline, Lavasa  applied afresh for environmental clearance to the first phase of its Rs 3000-crore hill city project near Pune, which is being considered by a high-level committee.

"They (Lavasa) have applied for phase-I clearance, which is being considered," Environment Minister Jairam Ramesh said today.

He said the matter is being considered by the Expert Appraisal Committee (EAC).

"Phase I is 2000 hectares. Phase II is 3000 hectares.
And if I recall right....today the application for the 2000 hectares is being considered. And two weeks from now... three weeks from now... the application for the next phase, which is already on...3000 hectares...will be considered," the minister said.

Asked when the decision was expected, the Minister said, "I don't know. The committee is meeting. I don't interfere in their function. They are meeting for deciding for the phase I clearance."
He said Lavasa did not get the clearance from environment view point.

"They went to court. The matter is in court. It is now they have applied for the environmental clearance. Today and tomorrow it is being considered in our ministry. It is going through the due diligence process now," Ramesh said.

The Environment Ministry last month had held that the controversial project was "unauthorised" and had directed the Lavasa Corporation Limited to maintain status-quo at the construction site.

However, providing a ray of hope for Lavasa, the Ministry had said it was prepared to consider the project being constructed near Pune on "merits" subject to fulfilment of certain conditions even as it ordered that no further construction should be undertaken for now.

On January 18, the Ministry in its order had said it was prepared to consider the project subject to imposition of penalties, creation of Environmental Restoration Fund (ERF), formulation of a comprehensive Environmental Impact Assessment (EIA) and the management plan.
first published: Feb 15, 2011 10:00 am

Discover the latest Business News, Sensex, and Nifty updates. Obtain Personal Finance insights, tax queries, and expert opinions on Moneycontrol or download the Moneycontrol App to stay updated!

Subscribe to Tech Newsletters

  • On Saturdays

    Find the best of Al News in one place, specially curated for you every weekend.

  • Daily-Weekdays

    Stay on top of the latest tech trends and biggest startup news.

Advisory Alert: It has come to our attention that certain individuals are representing themselves as affiliates of Moneycontrol and soliciting funds on the false promise of assured returns on their investments. We wish to reiterate that Moneycontrol does not solicit funds from investors and neither does it promise any assured returns. In case you are approached by anyone making such claims, please write to us at grievanceofficer@nw18.com or call on 02268882347