23 state RERA authorities extend registration of projects by 6-9 months

Measure taken to safeguard interests of homebuyers, ensure that projects do not get stalled due to disruptions caused by COVID-19 pandemic and flats get delivered albeit with some delay, he said in a series of tweets

June 17, 2020 / 13:26 IST

As many as 23 state RERA Authorities have so far extended registration of projects by six months and one by nine months following the situation created by the coronavirus pandemic and this has been done to safeguard the interests of homebuyers, housing and urban affairs secretary Durga Shanker Mishra has tweeted.

As advised by the ministry, this has been done ‘suo moto’ to cut down unnecessary paperwork and delay, he said.

“Interests of homebuyers have got squarely ensured via extension. RERA is to safeguard interests of homebuyers and that has been done,” he tweeted.

Homebuyers with lifetime savings invested in dream home project are interested in flats/homes and not litigation or ‘making developers get failed,’ he said in a series of tweets.

He noted that some citizens had raised concerns on social media against the extension given to real estate projects through the ministry’s advisory to states/RERA to complete the projects.

COVID-19 Vaccine

Frequently Asked Questions

View more
How does a vaccine work?

A vaccine works by mimicking a natural infection. A vaccine not only induces immune response to protect people from any future COVID-19 infection, but also helps quickly build herd immunity to put an end to the pandemic. Herd immunity occurs when a sufficient percentage of a population becomes immune to a disease, making the spread of disease from person to person unlikely. The good news is that SARS-CoV-2 virus has been fairly stable, which increases the viability of a vaccine.

How many types of vaccines are there?

There are broadly four types of vaccine — one, a vaccine based on the whole virus (this could be either inactivated, or an attenuated [weakened] virus vaccine); two, a non-replicating viral vector vaccine that uses a benign virus as vector that carries the antigen of SARS-CoV; three, nucleic-acid vaccines that have genetic material like DNA and RNA of antigens like spike protein given to a person, helping human cells decode genetic material and produce the vaccine; and four, protein subunit vaccine wherein the recombinant proteins of SARS-COV-2 along with an adjuvant (booster) is given as a vaccine.

What does it take to develop a vaccine of this kind?

Vaccine development is a long, complex process. Unlike drugs that are given to people with a diseased, vaccines are given to healthy people and also vulnerable sections such as children, pregnant women and the elderly. So rigorous tests are compulsory. History says that the fastest time it took to develop a vaccine is five years, but it usually takes double or sometimes triple that time.

View more
Show

“This has been done as an essential measure to safeguard the interest of homebuyers,” he said.

With COVID-19 having impacted construction work, real estate projects will take quite some time to resume fully.

“Due to COVID-19 works of ongoing real estate projects have halted. Large-scale reverse migration of labour and huge disruptions in supply chain of materials have adversely impacted construction works. Labour is least likely to return before festivals in October-November get over,” he tweeted.

In such circumstances, real estate projects will take quite some time to resume work fully. Surely this will delay completion leading to lot of litigations for non-compliance of commitments on time and make projects fail/get stressed, he said.

Hence, in order to safeguard the interest of all stakeholders, especially homebuyers and to ensure delivery of houses/flats to them, the ministry had advised states/RERA to invoke the force majeure clause under the law, the tweet said.

He also said that the RBI had allowed a moratorium of six months until August 31 to homebuyers for the payment of dues in view of the coronavirus. Hence, borrowers get effectively nine months to put their accounts in order without getting NPA.

“These measures have been taken to ensure that projects do not get stalled due to disruptions caused by COVID-19 pandemic and flats/homes get delivered to the homebuyers albeit with some delay,” the tweet said.

The Centre, on May 13, issued an advisory asking real-estate regulators in states and union territories to extend by at least six months the deadline for completion of projects in the face of the coronavirus outbreak.

The outbreak of COVID-19, the respiratory illness caused by the coronavirus, be treated as an “act of God” and a “force majeure” event under the Real Estate Regulatory Authority (RERA) Act, the housing and urban affairs ministry said in the advisory.

The deadline for RERA projects that were registered or were to be completed by or on March 25 be extended, it said, giving relief to the stressed sector. The advisory came a few hours after Finance Minister Nirmala Sitharaman told media that the deadline would be extended.

The Rajasthan Real Estate Regulatory Authority became the first authority to have issued the order extending by a year the deadline of projects registered before March 19, 2020, waiving off the fee for the extended period.

Maharashtra RERA and Gujarat RERA authorities have extended by six months the completion deadlines for real estate projects in their respective states.

UP RERA also extended the deadline for completion of real estate projects by six months in the face of the coronavirus outbreak.

Meanwhile, pointing out that extension of project timelines comes with an additional burden of EMIs, rent and mental agony, homebuyers in a letter to prime minister Narendra Modi had said last month that the Centre’s advisory asking real-estate regulators (RERA) in states and union territories to extend by at least six months the deadline for completion of projects in the face of the coronavirus outbreak is “illegal and beyond the powers under the law.”

Homebuyers, had requested the PM to issue directions to MoHUA to modify its advisory on force majeure due to Covid-19, to be in line with section 6 of RERA, and that to only for the actual period of lockdown when construction was not permitted, without any further liberty to the authorities to extend.

“Anything other than this, is patently illegal and should not be promoted by the very custodians of the law,” the letter said.

“It has become a practice amongst the regulatory authorities to provide indiscriminate extension to real estate projects without following the requirements of the law (Section 6), which clearly stipulates that an extension can only be given ‘when there is no default on the part of developers and only on grounds of Force Majeure’.

Vandana Ramnani
Vandana Ramnani
first published: Jun 17, 2020 01:26 pm

Discover the latest Business News, Sensex, and Nifty updates. Obtain Personal Finance insights, tax queries, and expert opinions on Moneycontrol or download the Moneycontrol App to stay updated!

Subscribe to Tech Newsletters

  • On Saturdays

    Find the best of Al News in one place, specially curated for you every weekend.

  • Daily-Weekdays

    Stay on top of the latest tech trends and biggest startup news.

Advisory Alert: It has come to our attention that certain individuals are representing themselves as affiliates of Moneycontrol and soliciting funds on the false promise of assured returns on their investments. We wish to reiterate that Moneycontrol does not solicit funds from investors and neither does it promise any assured returns. In case you are approached by anyone making such claims, please write to us at grievanceofficer@nw18.com or call on 02268882347