The task of demolishing the twin towers was made more difficult by the presence of other residential buildings nearby.
It was an intense day for those involved in the demolition, with emotions running high amid a lot of mental and physical effort.
A homebuyer is trapped in the builder’s net the moment he pays the token amount. Thereon, he has no choice but to succumb to the builder’s wishes.
The demolition of the Apex and Ceyane towers was the biggest of its kind in the country. More than 3,700 kg of explosives were used on Sunday to raze the buildings which were taller than Qutub Minar.
Around 80,000 tonnes of debris have been generated, of which 50,000-55,000 tonnes will be used to fill the crater left behind by the buildings and the rest will be sent to a construction and demolition plant for processing
The Noida-Greater Noida Expressway will be closed for 30 minutes and be opened once the dust settles, DCP (traffic) Ganesh Prasad Saha has said. Some roads that have been closed since morning and will be reopened depending on the dust situation
As we get ready to see the demolition live, let's get familiar with some terms relevant to the demolition process
Our specially curated package of the most interesting articles to help you stay at the top of your game.
Explosives have reportedly been fixed in the smaller of Supertech’s twin towers in Noida, slated for demolition on August 28.c
The Twin Towers of Noida will be razed soon as the last date for demolishing is set on August 28th, 2022. However, there is an issue. There are two buildings in close proximity. One of them is just 9 meters away. So, how will the demolition take place? What security measures will be adopted?
The test blast was carried out to determine the exact quantity of explosives needed on May 22 to bring down the two 40-storeyed buildings in Noida, declared illegal by the Supreme Court.
The purpose of the test explosion is to optimise the quantity of explosives to be used for the actual demolition on May 22. An estimated 2,500 kg to 4,000 kg of explosives may be required.
The action has come close on the heels of the Supreme Court's order for demolition of Supertech's illegal twin towers in Sector 93A in a verdict that also brought severe flak for the Noida Authority.