The company has planned to add 1 GW capacity this fiscal, ReNew Power Venture Chairman and CEO Sumant Sinha told PTI. It has installed generation capacity of 2.4 GW, at present. "We are aiming at 5 GW power generation capacity in the next two years time. We have planned to add 1 GW during this fiscal," Sinha said.

September 10, 2017 / 10:41 IST

Renewable energy firm ReNew Power Ventures targets to double its generation capacity to 5 GW in the next two years, a top company official said.

The company has planned to add 1 GW capacity this fiscal, ReNew Power Venture Chairman and CEO Sumant Sinha told PTI. It has installed generation capacity of 2.4 GW, at present. "We are aiming at 5 GW power generation capacity in the next two years time. We have planned to add 1 GW during this fiscal," Sinha said.

"We have sufficient funds to meet our expansion requirement during the current fiscal," Sinha said. An estimated investment of Rs 10,000 crore would be required to double the capacity to 5 GW.

In April, ReNew Power Ventures had announced doubling its power generation capacity in a year's time, which crossed 2 GW. The company invested Rs 6,700 crore (USD 1 billion) to add 430 MW of solar and 626 MW of wind capacity in 2016-17.

Asked about reasonable solar power tariff in current scenario as solar module prices have started inching upwards, Sinha opined that it should be Rs 2.75 per unit.

Earlier this year in May, solar power tariff had dropped to all-time low of Rs 2.44 per unit in the auction conducted for Bhadla solar park.

At that time, industry experts have said that lower borrowing cost and solar equipment prices have pulled down the tariff to historic low of Rs 2.44 per unit.

Similarly, the wind power tariff also plunged to Rs 3.46 per unit in an auction for 1GW capacity conducted by the Solar Energy Corporation of India (SECI).

SECI is in the process of putting 3 GW wind capacities on the block for auction. The SECI is waiting for Central Electricity Regulatory Commission's clarification on the inter-state connectivity trading. In the absence of evacuation facility of power from these projects, the developers are hesitant to go ahead.

first published: Sep 10, 2017 10:15 am

Discover the latest Business News, Sensex, and Nifty updates. Obtain Personal Finance insights, tax queries, and expert opinions on Moneycontrol or download the Moneycontrol App to stay updated!

Subscribe to Tech Newsletters

  • On Saturdays

    Find the best of Al News in one place, specially curated for you every weekend.

  • Daily-Weekdays

    Stay on top of the latest tech trends and biggest startup news.

Advisory Alert: It has come to our attention that certain individuals are representing themselves as affiliates of Moneycontrol and soliciting funds on the false promise of assured returns on their investments. We wish to reiterate that Moneycontrol does not solicit funds from investors and neither does it promise any assured returns. In case you are approached by anyone making such claims, please write to us at grievanceofficer@nw18.com or call on 02268882347