KRERA orders Embassy Group to compensate buyers Rs 4 crore for delay in luxury Bengaluru project

According to Karnataka RERA documents, the RERA registration period for the project Embassy One was 2019. However, the authority granted an extension for 9 months in 2020 due to the Covid-19 pandemic. When the developer failed to complete the project even by that date, the authority extended it till 2026 in March 2024.

June 27, 2024 / 17:01 IST
hile the handover date was 2018, the developer failed to offer possession even after six years of the promised handover date.

The Karnataka Real Estate Regulatory Authority (KRERA) has asked Embassy One Developers Pvt Ltd, a subsidiary of the Bengaluru-based Embassy Group, to pay Rs 4.2 crore in delayed compensation to homebuyers after it failed to deliver possession five years after the agreed handover date.

The authority noted that for the luxury Embassy One project in north Bengaluru, the developer had failed to file objections despite seeking three months from KRERA. Thus it ordered the developer to pay the compensation from the date of the promised handover to the date of possession. "Additionally, the developer will have to pay interest for further delay in completion of the project," it added.

In this case, the homebuyer Poonam Prabhu had booked the apartment in the luxurious Embassy One project for Rs 7.8 crore in 2016. The handover date was 2018, but the developer failed to offer possession even after six years of the promised handover date.

Located in north Bengaluru, Embassy One is a premium luxury project sprawling over more than six acres and has 109 apartments. The units are spread across two towers and offer 1-5 BHK options.

"It is evident that the homebuyer has paid a large amount for the apartment and there is a delay in handing over the apartments. Hence, the developer is entitled to pay delay interest according to Section 18 of the RERA Act," the order said.

"Embassy Group has challenged the KRERA order in the Karnataka High Court and obtained an interim stay until further orders on June 18. The rest of the matter is subjuidice," a company spokesperson added.

According to Karnataka RERA documents, the RERA registration period for the project Embassy One was 2019. However, the authority granted an extension for 9 months in 2020 due to the Covid-19 pandemic. When the developer failed to complete the project even by that date, the authority extended it till 2026 in March 2024.

Data from the authority shows that the developer currently has more than 11 complaints lodged against them in Bengaluru and a majority of them have been settled out of the court.

Souptik Datta Reports on Bengaluru, Hyderabad, and Chennai. Btw, curiosity never kills the cat. You can reach me on souptikdatta@nw18.com
first published: Jun 26, 2024 04:12 pm

Discover the latest Business News, Sensex, and Nifty updates. Obtain Personal Finance insights, tax queries, and expert opinions on Moneycontrol or download the Moneycontrol App to stay updated!

Subscribe to Tech Newsletters

  • On Saturdays

    Find the best of Al News in one place, specially curated for you every weekend.

  • Daily-Weekdays

    Stay on top of the latest tech trends and biggest startup news.

Advisory Alert: It has come to our attention that certain individuals are representing themselves as affiliates of Moneycontrol and soliciting funds on the false promise of assured returns on their investments. We wish to reiterate that Moneycontrol does not solicit funds from investors and neither does it promise any assured returns. In case you are approached by anyone making such claims, please write to us at grievanceofficer@nw18.com or call on 02268882347