India may give reprieve to solar projects delayed by coronavirus fallout

Anand Kumar, India's renewable energy secretary, said all the contracts have a 'force majeure' clause that companies can invoke to secure an extension on the project schedules.

February 18, 2020 / 22:08 IST
Representative image

India will consider extending deadlines for completing solar energy projects to shield developers from stiff penalties after the coronavirus outbreak hit component supplies from China, a top government official said on Tuesday.

Ratings agency Standard and Poor's Indian unit, Crisil, warned on Monday that nearly three gigawatts of solar power projects worth $2.24 billion could be at risk of penalties for missing a July 2020 completion deadline as the coronavirus hit solar industry supplies.

India buys about 80% of its solar modules from China, which has shut down some factories, restricted transport and implemented other measures to combat the spread of the virus that has killed 1,868 people in China and infected 72,436 others.

Anand Kumar, India's renewable energy secretary, said all the contracts have a 'force majeure' clause that companies can invoke to secure an extension on the project schedules.

"We will definitely consider the applications of developers for an extension of timelines provided there is evidence (to prove that the project has been affected due to coronavirus)," Kumar told Reuters.

COVID-19 Vaccine

Frequently Asked Questions

View more
How does a vaccine work?

A vaccine works by mimicking a natural infection. A vaccine not only induces immune response to protect people from any future COVID-19 infection, but also helps quickly build herd immunity to put an end to the pandemic. Herd immunity occurs when a sufficient percentage of a population becomes immune to a disease, making the spread of disease from person to person unlikely. The good news is that SARS-CoV-2 virus has been fairly stable, which increases the viability of a vaccine.

How many types of vaccines are there?

There are broadly four types of vaccine — one, a vaccine based on the whole virus (this could be either inactivated, or an attenuated [weakened] virus vaccine); two, a non-replicating viral vector vaccine that uses a benign virus as vector that carries the antigen of SARS-CoV; three, nucleic-acid vaccines that have genetic material like DNA and RNA of antigens like spike protein given to a person, helping human cells decode genetic material and produce the vaccine; and four, protein subunit vaccine wherein the recombinant proteins of SARS-COV-2 along with an adjuvant (booster) is given as a vaccine.

What does it take to develop a vaccine of this kind?

Vaccine development is a long, complex process. Unlike drugs that are given to people with a diseased, vaccines are given to healthy people and also vulnerable sections such as children, pregnant women and the elderly. So rigorous tests are compulsory. History says that the fastest time it took to develop a vaccine is five years, but it usually takes double or sometimes triple that time.

View more
Show

Some of the companies running up against the July 2020 deadline include Aditya Birla Renewables and SoftBank-backed SB Energy.

Acme Solar also has solar projects but said it did not face a July 2020 deadline.

"None of our projects are affected due to the coronavirus," said a spokesman for Acme Solar.

"We have executed all our projects on time always and we will continue to execute our projects in the pipeline on time," the spokesman said.

Aditya Birla Renewables and SB Energy did not respond to emails on Tuesday asking if they would meet the project completion deadlines.

Indian rules impose monetary penalties for a three-month delay in commissioning of a project, while projects delayed further also face downward revisions in tariffs.

Tariffs at which a company will sell the power to customers are quoted when the developer bids for a project.

"We cannot predict when China will start production of solar modules and cells," said C. Narasimhan, president of the Indian Solar Association. "The government should look at extending the deadline without renegotiating the tariff."

Purchasing of solar modules from elsewhere would be between 15% and 20% more costly, and could erode returns from the affected projects, said Crisil, without identifying individual projects.

Orders for modules are mostly placed six months ahead of the start of commercial operations.

Narasimhan, who also heads Raasi Group, which is building a 100-megawatt solar power project at Tamil Nadu in southern India, said Raasi was also requesting an extension to avoid facing any penalties, including a downward revision in tariffs.

"We're discussing it with state government officials ... as this particular situation is beyond our control." he said.

 

Reuters
first published: Feb 18, 2020 10:04 pm

Discover the latest Business News, Sensex, and Nifty updates. Obtain Personal Finance insights, tax queries, and expert opinions on Moneycontrol or download the Moneycontrol App to stay updated!

Subscribe to Tech Newsletters

  • On Saturdays

    Find the best of Al News in one place, specially curated for you every weekend.

  • Daily-Weekdays

    Stay on top of the latest tech trends and biggest startup news.

Advisory Alert: It has come to our attention that certain individuals are representing themselves as affiliates of Moneycontrol and soliciting funds on the false promise of assured returns on their investments. We wish to reiterate that Moneycontrol does not solicit funds from investors and neither does it promise any assured returns. In case you are approached by anyone making such claims, please write to us at grievanceofficer@nw18.com or call on 02268882347