India's clean energy industry opposes revocation of connectivity over delays

India aims to add 500 GW of non-fossil capacity by 2030, but delays in project execution and transmission constraints have emerged as major hurdles

January 16, 2026 / 09:09 IST
The country's transmission network — about 495,000 circuit kilometres — is struggling to keep pace with the rapid growth in renewable generation.
Snapshot AI
  • Renewable groups oppose CERC plan to strip grid access over unsigned PPAs
  • Industry warns auctioning grid access could raise tariffs and favor big players
  • Groups urge longer deadlines and focus on timely PPA signing, not penalties

India's renewable energy groups have objected to a regulatory proposal that could strip developers of interstate transmission system connectivity if long-term power purchase agreements are not timely signed, letters to the power regulator showed.

The groups said the Central Electricity Regulatory Commission's (CERC) move would unfairly penalise projects stalled for reasons beyond their control.

A CERC staff paper issued in November said more than 45 GW of renewable capacity currently holds grid connectivity based on letters of award but has not progressed to power purchase agreements, blocking transmission bays needed for new projects.

The paper proposed options such as auctioning surrendered capacity and deeming connectivity surrendered if PPAs remain unsigned for more than 12 months.

India aims to add 500 GW of non-fossil capacity by 2030, but delays in project execution and transmission constraints have emerged as major hurdles.

The country's transmission network — about 495,000 circuit kilometres — is struggling to keep pace with the rapid growth in renewable generation.

The National Solar Energy Federation of India said auctioning vacated connectivity at a premium would raise tariffs and favour financially stronger players, arguing that grid access "cannot become a tradable commodity."

It said delays in PPA signing stem largely from slow tariff adoption and approval processes at state distribution companies.

Wind-sector groups, including the Indian Wind Turbine Manufacturers Association and the Indian Wind Energy Association, said the proposed 18-month deadline to complete wind projects is unrealistic.

They noted that turbines and other equipment take long to manufacture and are often imported, adding to delays. They urged CERC to allow 24–30 months to complete projects instead of 18 months.

Government tendering agency Solar Energy Corporation of India also opposed premium-based auctions, warning they could inflate future tariffs.

The SECI suggested reallocating connectivity based on project readiness — land, financial closure and equipment status — rather than awarding it to the highest bidder.

Industry groups urged CERC to shift focus from penalising developers to ensuring timely signing by working with the power and renewable-energy ministries.

Reuters
first published: Jan 16, 2026 09:09 am

Discover the latest Business News, Sensex, and Nifty updates. Obtain Personal Finance insights, tax queries, and expert opinions on Moneycontrol or download the Moneycontrol App to stay updated!

Subscribe to Tech Newsletters

  • On Saturdays

    Find the best of Al News in one place, specially curated for you every weekend.

  • Daily-Weekdays

    Stay on top of the latest tech trends and biggest startup news.

Advisory Alert: It has come to our attention that certain individuals are representing themselves as affiliates of Moneycontrol and soliciting funds on the false promise of assured returns on their investments. We wish to reiterate that Moneycontrol does not solicit funds from investors and neither does it promise any assured returns. In case you are approached by anyone making such claims, please write to us at grievanceofficer@nw18.com or call on 02268882347