Light at the end of the tunnel? Bengaluru Metro's Pink Line likely to be ready by next year

BMRCL plans to open the Pink Line in two phases: 7.5 km elevated section from Kalena Agrahara to Tavarekere by December 2025 and 13.8 km underground section from Dairy Circle to Nagawara by December 2026

February 17, 2025 / 18:54 IST
MG Road UG Metro station

Beneath Bengaluru’s bustling Kamaraj Road, 60 feet below the surface, tracks have been laid, and civil work is progressing as the MG Road underground station of the Pink Line takes shape.

Pink Line connects Nagawara on the Outer Ring Road in the north to Kalena Agrahara on Bannerghatta Road in the south.

Speaking to reporters at MG Road underground Metro station, Subrahmanya Gudge, chief Engineer (underground section) at Bangalore Metro Rail Corporation Limited (BMRCL), said that tunnelling in Bengaluru is extremely challenging.

Also, readBengaluru Metro completes tunnelling work on city’s longest underground section

He explained that the presence of boulders in the soil is a frequent obstacle during tunnelling.

“Granite boulders are particularly hard, with a Uniaxial Compressive Strength (UCS) of 150 megapascals (MPa), while dolerite boulders are even harder, with a UCS of 300 MPa. When boulders are smaller than the cutter head of the tunnel boring machine (TBM), they rotate with the machine, damaging the cutting tools. This not only damages the tools but also causes ground settlement and leads to the accumulation of boulders in the cutting chamber” he said.

Gudge added that tunnelling through the Central Business District, specifically between Shivaji Nagar to Vellara (2.2 km), has been the most challenging part of Namma Metro’s Phase 2 underground section.

“The challenging geological conditions forced us to replace 799 cutter discs on this section. This is needed when discs wear out or are required to cut through rocky soil. The route's mix of rock and soil causes frequent disc replacements, as the discs mounted on the Tunnel Boring Machines are damaged by hard rock or boulders. Each cutter disc costs between Rs 1.5 lakh and Rs 3 lakh, and most are beyond repair” said Gudge.

In October 2024, Bengaluru Metro completed the tunnelling work for the city’s longest 14 km underground section of the Pink Line, which is part of Phase 2 of the project.

Officials said that more than 90 percent of the civil and track laying work has been completed. However, there is still pending work, including station construction, signalling, telecommunications, traction power supply, air-conditioning systems, lifts, and escalators.

Although the length of the underground section is 14 km, the total tunnel length involved is 21 km, as there are twin tunnels.

This underground section is part of Bengaluru Metro's 21.3 km Pink Line, which is a combination of 13.8 km of underground and 7.5 km of elevated sections, connecting Nagawara on the Outer Ring Road in the north to Kalena Agrahara on Bannerghatta Road in the south.

BMRCL officials plan to open the Pink Line in two phases. The first phase, which is a 7.5 km elevated section from Kalena Agrahara (Gottigere) to Tavarekere (Swagath Cross), is expected to open by December 2025. The second phase, which is a 13.8 km underground section connecting Dairy Circle to Nagawara, is expected to open by December 2026.

Also, readBengaluru Metro's Pink Line to be operational in two phases

In August 2023, Bharat Earth Movers Limited (BEML) had received a rolling stock order worth Rs 3,177 crore from BMRCL, which includes 96 coaches for the Pink Line. BEML is expected to supply the prototype train for the Pink Line by October 2025.

Moneycontrol News
first published: Feb 17, 2025 06:53 pm

Discover the latest Business News, Sensex, and Nifty updates. Obtain Personal Finance insights, tax queries, and expert opinions on Moneycontrol or download the Moneycontrol App to stay updated!

Subscribe to Tech Newsletters

  • On Saturdays

    Find the best of Al News in one place, specially curated for you every weekend.

  • Daily-Weekdays

    Stay on top of the latest tech trends and biggest startup news.

Advisory Alert: It has come to our attention that certain individuals are representing themselves as affiliates of Moneycontrol and soliciting funds on the false promise of assured returns on their investments. We wish to reiterate that Moneycontrol does not solicit funds from investors and neither does it promise any assured returns. In case you are approached by anyone making such claims, please write to us at grievanceofficer@nw18.com or call on 02268882347