| Particulars | Details |
|---|---|
| Name of Entity Awarding Order | Delhi Metro Rail Corporation Limited |
| Nature of Order | CONTRACT D2C-02: Part Design and Construction of viaduct of length 7.298 kms. from Chainage 1202.782 M to Chainage 8501.25 M including seven (07) stations (only platforms) namely Pushp Vihar, Saket District Court, Pushpa Bhawan, Chirag Delhi, GK-1, Andrews Ganj And Lajpat Nagar including Pre-Engineered Building Structure in all stations of Lajpat Nagar to Saket G block corridor of Delhi MRTS Phase-IV Project. |
| Order Type | Domestic |
| Execution Time Period | 36 Months |
| Project Cost | ₹447,42,48,757.33 (inclusive of 18% GST) |
| Related Party Transaction | No |
Project Overview
The project includes the construction of a 7.298 km viaduct from Chainage 1202.782 M to Chainage 8501.25 M. It also involves the construction of seven stations (only platforms): Pushp Vihar, Saket District Court, Pushpa Bhawan, Chirag Delhi, GK-1, Andrews Ganj, and Lajpat Nagar. The construction includes pre-engineered building structures in all stations from Lajpat Nagar to Saket G block corridor of Delhi MRTS Phase-IV Project.
Financial Details
The project is valued at ₹447,42,48,757.33, which includes 18% GST. The project is expected to be completed within 36 months.
Strategic Importance
This contract is part of the Delhi MRTS Phase-IV Project, which aims to expand and improve the metro network in Delhi. The project will enhance connectivity and provide better transportation infrastructure for the city's residents.
Market Impact
The acquisition of this project is a positive development for Rail Vikas Nigam Limited, demonstrating its capabilities in executing large-scale infrastructure projects. This contract is expected to contribute to the company's revenue and strengthen its position in the railway and metro construction sector.