HomeNewsBusinessNoida Twin Towers Demolition: Only around 1 percent of the construction debris has reached C&D waste recycling plant
Trending Topics

Noida Twin Towers Demolition: Only around 1 percent of the construction debris has reached C&D waste recycling plant

Environmentalists say at the current pace, the promise of recycling 30,000 tonnes before the end of November is unlikely to be met, and may take up to one year. They also plan to move the National Green Tribunal if authorities fail to meet the target. 

September 30, 2022 / 19:10 IST
Story continues below Advertisement

One month after the Supertech twin towers vanished from the Noida skyline, having been demolished on the order of the Supreme Court, only about 400 tonnes of construction and demolition (C&D) waste has reached the recycling plant in Noida’s Sector 80, or about 1.3 percent of the target 30,000 tonnes to be taken to the plant by November 2022, sources said.

Sources said that on September 29, about 150 tonnes of C&D waste reached the recycling plant.

Story continues below Advertisement

Officials in Edifice Engineering, the company that carried out the demolition, said about 18 truckloads of debris have been transported already. This is after the Noida Authority on Wednesday ordered the company to remove the debris.

In a statement on September 28, the Noida Authority said, “The work of moving the construction and demolition waste should start by the Edifice Engineering from September 29, and should be completed by November 28, as per the Supreme Court orders.”