Bengaluru Metro's Pink Line to start with 5 'driverless' trains by June

BEML will roll out the prototype train for the Pink Line (Kalena Agrahara–Nagawara) on December 11, which will then undergo rigorous tests for at least five months before being deployed

December 10, 2025 / 15:12 IST
Story continues below Advertisement

Bengaluru Metro’s 7.5-km elevated section of Pink Line (Kalena Agrahara-Tavarekere) will begin operations with five “driverless-capable” trains by June, with the prototype to be unveiled on December 11, sources told Moneycontrol.

The remaining 13.7-km underground section between Dairy Circle and Nagawara is expected to be ready by December next for the much-delayed line.

Story continues below Advertisement

“We will open the elevated section of Pink Line with five trains by June 2026. All 16 trains will be delivered for Pink Line by the time the entire stretch (Kalena Agrahara-Nagawara) is opened for commercial service in December 2026,” a BMRCL official told Moneycontrol.