Work on 14,000 Amrapali units in progress; handover of 160 units in September, says NBCC

Work on all projects are likely to be completed within 9 to 36 months. Completion depends on timely deposit by homebuyers and arrangement of funds from other sources, says NBCC CMD PK Gupta.

August 24, 2020 / 20:25 IST
Story continues below Advertisement

In a relief to homebuyers waiting for their homes, the government’s construction arm – NBCC – has said that work on eight projects in Noida and Greater Noida by the embattled real estate firm Amrapali Group that include over 14,000 residential units is currently in progress and around 160 units are likely to be handed over in September.

Work on 16,000 units in Greater Noida commenced on August 24 following a bhoomi poojan ceremony in the presence of Supreme Court-appointed court receiver and senior advocate R Venkataramani, who has been entrusted with the task of managing the affairs of the Amrapali Group.

Story continues below Advertisement

Work is currently on in eight projects in Noida involving 11,741 units in Silicon-1 and 2, Silicon-Crystal Homes, Sapphire I and II, Princely, Platinum/Titanium and Zodiac and three projects in Greater Noida- Centurian Park-Low rise and O2 Valley, Leisure Valley Villa and Dream Valley villas involving 2,666 units is in progress, NBCC officials said.

NBCC has started handing over of flats to homebuyers in these projects and around 160 units are likely to be handed over in the first week of September. As many as 73 units have already been handed over, the officials said.