HomeNewsBusinessReal EstateSC modifies NCDRC order for delayed project in Bengaluru, directs developer to pay interest, compensation

SC modifies NCDRC order for delayed project in Bengaluru, directs developer to pay interest, compensation

About 62 homebuyers who had purchased apartments in the Mantri Serenity project had filed an appeal in the Supreme Court challenging the initial dates for the calculation of delayed interest, as per the NCDRC order passed in 2020.

August 18, 2023 / 15:11 IST
Story continues below Advertisement
Real Estate
The court said that over and above the interest, buyers shall also be paid compensation on account of delayed possession at the rate of Rs 3 per square foot per month from the agreed date of possession.

In a major relief to homebuyers, the Supreme Court, while modifying a previous National Consumer Disputes Redressal Commission (NCDRC) order, has directed Bengaluru-based developer Mantri Castles Pvt Ltd to pay 6 percent interest to customers who have invested in their much-delayed Mantri Serenity project. The interest is to be paid from the date of possession according to the respective agreements (starting from December 2015) till February 19, 2023, the date on which the developer says he has handed over possession.

However, homebuyers claim that the project still lies incomplete without a permanent water or electricity supply. Additionally, while blocks 2,4, and 5 have obtained partial occupancy certificates (OC) blocks 1 and 3 do not have OCs. Last week, Karnataka's Department of Electrical Inspectorate sent a notice to the developer for running lifts without permission in two towers.

Story continues below Advertisement

"The award of interest at the rate of 6 percent per annum by the NCDRC is subject to the modification that interest shall be payable with effect from the respective dates mentioned in the agreements for the delivery of possession," the order dated July 25, 2023, said.

The court said that over and above the interest, buyers shall also be paid compensation on account of delayed possession at the rate of Rs 3 per square foot per month from the agreed date of possession.