NCLAT asks Suraksha Group to start work on Jaypee Wish Town project

The appellate tribunal said if Suraksha Group and YIEDA will not settle their issues by the next date of hearing on April 18, 2024 then the plea will be heard on merit and a judgment passed

March 08, 2024 / 17:16 IST
Story continues below Advertisement
NCLAT asks Suraksha Group to start construction at Jaypee Wish Town delayed project
NCLAT asks Suraksha Group to start construction at Jaypee Wish Town delayed project

Following an appeal from the homebuyers of Jaypee Wish Town housing society in Noida sector 128, the National Company Law Appellate Tribunal (NCLAT) has directed Mumbai-based Suraksha Group to commence construction activities on Jaypee Infratech Limited (JIL)’s already delayed project, people aware of the matter said.

The NCLAT also asked the monitoring committee, which is supervising the routine work at the project currently, to file a status report on the projects in Wish Town within two weeks.

Story continues below Advertisement

According to homebuyers, the construction activities are yet to start because of pending approval for Suraksha’s resolution plan from the Uttar Pradesh cabinet.

The Yamuna Expressway Industrial Development Authority (YEIDA) had in September 2023, approved Suraksha Group’s resolution plan to complete stuck realty projects of bankrupt Jaypee Infratech Limited (JIL) in Noida and Greater Noida with a rider that the realtor will have to pay additional compensation of about 64.7 percent towards land compensation to farmers.