Karnataka RERA orders developer to refund entire amount despite project completion. Here's why

In this case, the homebuyer had booked an apartment in the Sobha Valley View project in south Bengaluru for Rs 1.5 crore.

October 02, 2023 / 10:20 IST
Story continues below Advertisement
The developer had promised to deliver the project within 2019, according to the sale agreement signed with the homebuyer.
The developer had promised to deliver the project within 2019, according to the sale agreement signed with the homebuyer.

Despite having completed a project as per the construction timeline, the Karnataka Real Estate Regulatory Authority (KRERA) has ordered the listed developer Sobha Limited to refund the entire amount with an annual interest of 9 percent to a homebuyer.

"The respondent is directed to pay Rs 2.5 crore towards refund with 9 percent interest per annum," the order dated September 14 said.

Story continues below Advertisement

While the developer claimed to have completed the project on time, it could not execute the sale deed as the project was attached by the Income Tax Department under the Prohibition of Benami Property Transactions Act.