Solar energy firms accuse NTPC of delaying issue of CoDs

The National Solar Energy Federation of India has claimed that the power produced from these solar projects is being sold at concessional rates.

July 10, 2017 / 15:49 IST
Story continues below Advertisement

Employees row a boat as they examine solar panel boards at a pond in Lianyungang, Jiangsu Province, China, in this March 16, 2016 file photo. Global funds are cautiously venturing back into Chinese equities after prices collapsed to 4-1/2-year lows in February, taking advantage of cheaper valuations to buy stocks they believe will benefit from China's shift to a consumption-led economy. REUTERS/Stringer/Files ATTENTION EDITORS - THIS PICTURE WAS PROVIDED BY A THIRD PARTY. THIS PICTURE IS DISTRIBUTED EXACTLY AS RECEIVED BY REUTERS, AS A SERVICE TO CLIENTS. CHINA OUT. NO COMMERCIAL OR EDITORIAL SALES IN CHINA - RTSCXID

The National Solar Energy Federation of India (NSEFI) has alleged that state-run power giant NTPC and its trading arm NVVN are delaying issue of commercial operation date (CoD) certificate to solar projects. The CoD is a pre-requisite for selling power at the rate prescribed in the power purchase agreement.

The NSEFI has claimed that the power produced from these solar projects is being sold at concessional rates.

Story continues below Advertisement

"NTPC and its trading arm NVVN are delaying in providing CoD certificates to plants commissioned in March, 2017, even after three months of their commissioning, although contractually required to provide CoD from 30th day of commissioning," NSEFI said in a letter to power secretary. An NTPC spokesperson did not comment on the matter.

The Ministry of New & Renewable Energy (MNRE) in March 2015 under the National Solar Mission programme came up with a scheme for setting up of 3000 MW (Phase II, Batch II) of Solar power projects under state specific bundling scheme to be implemented through NTPC/NVVN. Cheap & Clean – How Solar Power May Shape The Future of Modern India

Around 1500 MW of solar power projects have been commissioned in the last three months out of entire 3000 MW awarded under the scheme.