MahaRERA directs homebuyers of delayed Mumbai project to exit only after completion

The real estate project was taken over by the association of allottees because the developer could not complete it in a time-bound manner.

October 18, 2022 / 13:52 IST
Story continues below Advertisement
Representational image.

The Maharashtra real estate regulator has directed homebuyers in a delayed project to withdraw from it only after the association of allottees that has taken over or another developer completes the construction of the apartments.

The Maharashtra Real Estate Regulatory Authority (MahaRERA) said the homebuyers must wait until the project is completed so that the association of allottees or the new developer can sell the apartments of those who want to exit and refund them. Placing a financial liability on the association or the new developer may further delay the project, it said.

Story continues below Advertisement

However, lawyers said there was no clarity on a fresh timeline for the association of allottees or the new developer to complete the project. One lawyer said the feasibility of the project may be affected if the association of allottees or the incoming developer is made liable to compensate for delays by the previous promoter.

The MahaRERA’s order came in a case involving homebuyers seeking a refund from the Vijay Group, the developer of the Victory Platinum project in Mumbai’s Kandivali area.