HomeNewsBusinessReal EstateBuilders cannot cite Force Majeure provision for delay in delivering projects: NCDRC

Builders cannot cite Force Majeure provision for delay in delivering projects: NCDRC

The consumer court says that buyers who had made substantial payment towards their flats cannot be penalised for the builder’s inability to collect payments from other flat buyers due to which the project was delayed.

November 09, 2021 / 07:19 IST
Story continues below Advertisement

The National Consumer Disputes Redressal Commission (NCDRC) has held that real estate builders cannot take recourse to the Force Majeure provision for delay in delivering projects and that homebuyers cannot be made to wait indefinitely for possession of their units.

In a case involving two buyers who had paid around Rs 5.68 crore each for 5,514 sq.ft apartments in a project by Pioneer Urban Land and Infrastructure Ltd located in Sector 62, Gurgaon, the NCDRC has ruled that the delay of the project by the builder appears to be “delaying tactics veiled as ‘Force Majeure’ conditions and seem to be an attempt to wriggle out of its contractual obligations,” the order said.

Story continues below Advertisement

The two buyers had booked the luxury units in 2012 for which possession was promised by March 2016 but possession was not handed over until 2018-19 despite the payments being made. The grievance of the buyers was that despite receiving more than 90 percent of the total consideration, the builder had failed to hand over possession of the flats within the promised time period and even possession in the near future seemed unlikely.

The court has directed the builder to refund the amount deposited by the builder along with compensation in the form of simple interest at 9 percent per annum from the date of each payment till the date of payment by the builder who will have to comply with the order within two months from the date of the order. There shall be no order as to costs, the order said.