COVID-19 impact | Highway builders in a bind over force majeure notification

Some local field officers and independent engineers are rejecting COVID-19 as a force majeure event in certain cases, according to the National Highway Builders Federation.

April 20, 2020 / 15:49 IST
Story continues below Advertisement
Since the lockdown rules have lifted significantly, I’m sure a lot of you are itching to go out on a road trip. If you’re in the market looking for something that will help ferry the entire family, here’s a list we think could make that choice easier.
Since the lockdown rules have lifted significantly, I’m sure a lot of you are itching to go out on a road trip. If you’re in the market looking for something that will help ferry the entire family, here’s a list we think could make that choice easier.

Even though the Ministry of Road Transport and Highways has declared COVID-19 as a force majeure event and informed National Highways Authority of India (NHAI) accordingly on March 25, NHAI has not issued a similar notification, leading to confusion at the ground level.

This has resulted in local field officers and independent engineers acting according to their discretion, to the extent of rejecting COVID-19 as a force majeure event in certain cases, according to the National Highway Builders Federation (NHBF).

Story continues below Advertisement

The force majeure clause in a contract provides temporary reprieve to a party from performing its obligations upon occurrence of a force majeure event. This typically includes war, terrorism, earthquakes, hurricanes, acts of government, explosions, fire, plagues or epidemics or a list of events as agreed by both parties.

Rejection of COVID-19 as force majeure event has serious implications on the rights available to highway builders under the concession or contract agreement and may further affect the projects.