CAG suggests better monitoring of rail projects

Taking note of the safety related works, CAG observed as many as 37 works related to Complete Track Renewal, Through Rail Renewal and Through Sleeper Renewal were included in the 145 completed works.

April 29, 2016 / 22:22 IST
Story continues below Advertisement

Taking note of slow progress in railway projects, Comptroller and Auditor General of India (CAG) has suggested the need to strengthen the mechanism for selection, periodical monitoring of works at every stage of execution like preparation of detailed estimate, tendering process and provision of fund.

While reviewing the status of 443 works introduced during 2009-10 to 2013-14 as New Services/New Instrument of Services through Supplementary Demands for Grants, CAG in its latest report observed that 62 works had not commenced even one to five years after their approval by the Parliament, According to the CAG, 145 works had been completed up to March 2015, 37 works had been dropped up to March 2015, seven works were closed/frozen, 169 works were in progress as of March 2015.

Story continues below Advertisement

Out of these, the audit found 140 works were sanctioned more than two years back.

Taking note of the safety related works, CAG observed as many as 37 works related to Complete Track Renewal, Through Rail Renewal and Through Sleeper Renewal were included in the 145 completed works.