HomeNewsIndiaNearly a year after unveiling, first Vande Bharat sleeper train yet to start passenger service
Trending Topics

Nearly a year after unveiling, first Vande Bharat sleeper train yet to start passenger service

 Unveiled in September 2024, the first Vande Bharat sleeper train manufactured by BEML is yet to commence passenger services, reportedly due to quality issues.

August 19, 2025 / 15:15 IST
Story continues below Advertisement
Vande Bharat sleeper

It has been nearly a year since the Vande Bharat sleeper train manufactured by BEML was unveiled, but it is yet to be cleared for passenger service.

On September 1, 2024, the prototype train was unveiled with much fanfare by Union railway minister Ashwini Vaishnaw at BEML’s Bengaluru facility. At the time, he said that passenger services would commence within three months after trial runs. However, multiple deadlines have been missed since then.

Story continues below Advertisement

Also, readIndia’s first Vande Bharat sleeper train likely to be operational by year-end

In a recent letter to BEML, ICF said the prototype Vande Bharat sleeper rake delivered in October 2024 had 106 issues flagged for rectification. Though BEML had assured fixes by June 30, 2025, the rework remains incomplete, delaying commercial rollout. ICF has asked BEML to expedite pending work and share a revised completion date.