Tashee Capital Gateway: The Gurugram development with closed doors

When Tashee Capital Gateway was launched in 2010, civilians and military personnel alike bought homes in the project on which the developer abruptly stopped construction in 2016, without specifying a reason. Their story is a cautionary tale for homebuyers.

August 04, 2022 / 16:32 IST
Story continues below Advertisement
A total of 538 residential units and 13 shops were to be completed by 2016, but so far not a single unit has been delivered.
A total of 538 residential units and 13 shops were to be completed by 2016, but so far not a single unit has been delivered.

For retired government official Vasudev Chaddha, 85, every passing day means diminishing hope.

Chaddha is one of the 475 buyers who invested their life savings in 2010 to purchase a unit in KNS Infracon Pvt Ltd’s Tashee Capital Gateway, spread over Sector 110 A and Sector 111 in Gurugram, at the border of the national capital Delhi.

Story continues below Advertisement

Twelve years on, the residential project is stuck. Many have paid 90 percent of the cost of a home in the project; some have even paid 100 percent.

“I bought a flat in Tower D in 2012 and took a loan of around Rs 50 lakh. Since then, I have been paying EMIs (equated monthly installments) as well as rent. The delivery was supposed to take place in 2016 but there is no hope left for us,” said Vikas Hooda, one of the buyers.