HomeNewsBusinessReal EstateDeveloper cannot escape liabilities of project completion after promoters change: NCDRC

Developer cannot escape liabilities of project completion after promoters change: NCDRC

The court overturned an order passed by the Karnataka Real Estate Regulatory Authority and directed the developer to refund homebuyers' money.

July 15, 2023 / 11:15 IST
Story continues below Advertisement

The National Consumer Disputes Redressal Commission (NCDRC) has held in the case of a Bengaluru-based developer that the promoter will be responsible for homebuyers' investments even after the project has been transferred to another company. Legal experts say that the judgment will set a precedent in protecting homebuyers' rights in delayed projects.

In this case brought against Bengaluru-based developers Nitesh Estates by a person who had paid for a house but hadn’t got possession by the promised date, the developer argued that it had transferred the entire Nitesh Cape Cod Project to INESA Ventures LLP through a Karnataka Real Estate Regulatory Authority (KRERA) order in April 2023.

Story continues below Advertisement

However, the commission noted that there was a delay of around seven years from the promised date of possession. The developer has definitely committed a deficiency of service under the Consumer Protection Act, said the order dated May 30.

The case