Delayed possession: Homebuyer can take possession and later claim for interest from developer, says Bombay HC

According to the RERA Act, 2016, homebuyers are entitled to a refund/interest if they wish to exit the project where the possession is delayed or where the homebuyer takes possession after delay by the developer

April 03, 2024 / 10:00 IST
Story continues below Advertisement
Pune real estate: The Bombay HC was hearing in case filed by developer for a project in Pune's Balewadi area.
Pune real estate: The Bombay HC was hearing in case filed by developer for a project in Pune's Balewadi area.

The Bombay High Court has ruled that a homebuyer can claim for interest for delayed possession from a developer under Section 18 of RERA Act even after taking possession of the flat.

The HC was hearing a case filed by a developer of a project in Pune’s Balewadi area against verdicts by Maharashtra Real Estate Appellate Tribunal (MREAT) that directed payment of interest for delayed possession. The developer had promised possession on two different dates including August 2016 and September 2017. However, the possession was given to the two homebuyers only in 2018.

Story continues below Advertisement

RERA Act on interest for delayed possession

According to the RERA Act 2016, a homebuyer is entitled to claim refund/interest if he or she wishes to exit the project where the possession is delayed or where the homebuyer takes possession after delay by the developer.