Close to 9,000 Amrapali housing units completed by NBCC; all projects to be handed over by 2025: Officials

There are pending issues over buyers’ unpaid dues and the utilisation of unused floor area ratio

May 23, 2023 / 21:05 IST
Story continues below Advertisement
The total amount required to complete all the Amrapali projects is estimated at Rs 8,000 crore
NBCC is working on 25 Amrapali projects at 17 locations

NBCC Ltd, the government-owned construction company tasked by the Supreme Court to complete stalled Amrapali projects amounting to around 38,000 housing units, has so far completed close to 9,000 units, company officials said. It has done so utilising the Rs 4,000 crore received from homebuyers, a consortium of banks and SBICAP Ventures, which manages the stressed assets fund of the government, the NBCC sources added.

The two challenges NBCC currently faces have to do with realisation of funds from homebuyers and the floor area ratio (FAR) issue, they told Moneycontrol.

Story continues below Advertisement

As many as 4,000 homebuyers had registered on the company’s customer portal but they have not been coming forward to pay up the dues. There is also some uncertainty about the projects’ unused portion of the FAR, which is used to determine the total floor area of a building in relation to the size of the plot.

NBCC is working on 25 Amrapali projects at 17 locations. It had taken over the incomplete projects of the Amrapali Group following a Supreme Court order in July 2019. “We have received close to Rs 4,350 crore through several sources of funding such as homebuyers’ dues (Rs 1,800 crore), consortium of banks (Rs 1,200 crore out of the sanctioned Rs 1,500 crore) and SBICap (Rs 650 crore sanctioned, of which Rs 300 crore has been received) and the remaining from attached properties that have been sold, and consumed around Rs 4,000 crore,” one of the persons said.