Only 7% of routes under RCS-UDAN scheme sustainable beyond 3-year concession period: CAG

As on February 9, 2023, after four rounds of bidding under UDAN, 467 routes have commenced, operationalising 70 airports, including two water aerodromes and nine heliports, the Ministry of Civil Aviation said

August 14, 2023 / 16:55 IST
Story continues below Advertisement
The CAG report also presented 16 recommendations to enhance the scheme's implementation in the future.

Only 54 routes or 7 percent of all awarded routes under the government's ambitious regional connectivity scheme (RCS), Ude Desh Ka Aam Nagrik (UDAN) have managed to sustain operations beyond the three-year concession period, the Comptroller and Auditor General (CAG) said in a report.

In its latest report on the Ministry of Civil Aviation's RCS-UDAN scheme, the auditor general pointed out that 52 percent (403 out of 774 routes) of the awarded routes were unable to commence operations.

Story continues below Advertisement

"Out of the 371 commenced routes, only 112 routes (30 percent) successfully completed the full concession period of three years," the CAG said in its report.

Of the 112 routes only 54 routes managed to sustain operations beyond the three-year concession period as of March 2023, the report added.