Titagarh plans to complete the order of 204 coaches within the timeline of March 2025.

February 19, 2024 / 16:05 IST
Story continues below Advertisement
The 19-km Yellow Line, connecting the tech hub of Electronics City to RV Road in South Bengaluru, is expected to be operational by September 2024.
The 19-km Yellow Line, connecting the tech hub of Electronics City to RV Road in South Bengaluru, is expected to be operational by September 2024.

Titagarh Rail Systems is on track to start supplying driverless train sets for Bengaluru Metro’s Yellow Line (RV Road-Bommasandra) from April, senior company officials told Moneycontrol on the condition of anonymity.

"Our assembly line is almost commissioned. The machines are all here. The work is all done, so now it's just under commissioning, and commissioning should be complete within the next 45 to 60 days, and immediately after that, the manufacturing starts," a senior company executive said.

Story continues below Advertisement

He added that Titagarh Rail Systems will supply two train sets of six coaches each every month to Bengaluru Metro Rail Corp (BMRCL) from April.

BMRCL has imported the first two sets of six-car trains (12 coaches) from China, while the remaining 204 coaches will be manufactured by Titagarh Rail in India.