Moneycontrol
HomeNewsBusinessBharatmala Phase 1 completion deadline extended by 6 years to 2027-28
Trending Topics

Bharatmala Phase 1 completion deadline extended by 6 years to 2027-28

The escalated cost of Bharatmala has been a cause of concern, and the Union Finance Ministry told MoRTH in 2023 not to award any new project under the scheme till there is Cabinet approval on the revised cost of the project.

August 12, 2024 / 18:48 IST
Story continues below Advertisement

The CAG noted that detailed project reports prepared by consultants were not appraised with due diligence.

The Union government has extended the deadline for completion of its flagship highway development project Bharatmala Phase-I to 2027-28, six years from the original schedule, the Ministry of Road Transport and Highways (MoRTH) said in its annual report.

The ministry, in the annual report 2023-24, said a revised financial proposal to construct 34,800 km of national highways in 31 states and UTs and more than 550 districts for the Bharatmala Pariyojana is under process for approval.

Story continues below Advertisement

The approval and bidding of national highways under the flagship Bharatmala programme recorded a shortfall of 34 percent in 2023-24, as the revised cost of the scheme was pending approval from the Cabinet. The move follows an over 100 percent increase in the estimate cost of the mega project to nearly Rs 11 trillion, and reflects the slowing of implementation, and financial constraints.

“Major shortfall was because of Bharatmala where the revised approval of the Cabinet could not be obtained,” the ministry said in its annual performance report.