HomeNewsPowerMandate for imported coal-based thermal power plants to operate under Section 11 of Electricity Act no longer in effect: Ministry sources

Mandate for imported coal-based thermal power plants to operate under Section 11 of Electricity Act no longer in effect: Ministry sources

The power ministry has started active consultations with generators and discoms to review the power demand and work a way out. However, the government is clear that if the need arises, the order may be re-issued.

January 09, 2023 / 20:59 IST
Story continues below Advertisement
Coal availability has been an issue. Most of the coal procurement is through the e-auction route, and, hence, there was a spike in electricity prices. (Representative image)
Coal availability has been an issue. Most of the coal procurement is through the e-auction route, and, hence, there was a spike in electricity prices. (Representative image)

There has been no further extension to the order which mandated imported coal-based power plants to operate and generate electricity to their full capacity under section 11 of the Electricity Act, senior officials of the ministry of power told Moneycontrol on January 9.

On May 5 last year, when the country’s power demand had suddenly soared and thermal power plants had inadequate domestic coal to run fully, the power ministry invoked an emergency clause of the Electricity Act (section 11) and asked all thermal power plants running on imported coal to open and generate to their full capacity. At that time, most of these imported coal-based thermal power plants were shut due to high International coal prices and also because their power purchase agreements (PPAs) did not have adequate provision for pass-through of the increased cost of generation. But, after the order, they had to mandatorily restart operations.

Story continues below Advertisement

This order was initially supposed to be valid till October 31, 2022. But, it was later extended to December 31, 2022.

On January 3 this year, the Central Electricity Regulatory Commission (CERC) ordered that plants running on imported coal should be compensated for supplying electricity under emergency circumstances. The order, though was issued in response to a petition filed by Tata Power Company Limited (TPCL), is expected to benefit power plants with a combined capacity of about 17 gigawatt (GW).