HomeNewsIndiaNoida Airport: Survey for phase II land acquisition likely in two weeks, says officer

Noida Airport: Survey for phase II land acquisition likely in two weeks, says officer

The second phase of the NIA is planned in an area of 1,365 hectare, of which around 1,185 hectare is owned by private persons, including farmers, of six villages -- Ranhera, Kureb, Dayanatpur, Karauli Bangar, Mundrah, and Birampur , an official said.

November 30, 2022 / 10:57 IST
Story continues below Advertisement
Noida International Airport will be India’s first net-zero emission airport. (Image: AP)
Noida International Airport will be India’s first net-zero emission airport. (Image: AP)

The survey for acquisition of land for the second phase of the upcoming Noida International Airport (NIA) is expected to begin in two weeks from now, according to officials.

Currently, construction work is underway for the first phase of the Greenfield airport in Jewar in Gautam Buddh Nagar as the Uttar Pradesh government recently gave its go ahead for land acquisition for the second phase, they said.

Story continues below Advertisement

The second phase of the NIA is planned in an area of 1,365 hectare, of which around 1,185 hectare is owned by private persons, including farmers, of six villages -- Ranhera, Kureb, Dayanatpur, Karauli Bangar, Mundrah, and Birampur , an official said.

The land is being acquired under the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013.