HomeNewsBusinessReal EstateWill NCLT’s approval of Ace Infracity resolution plan for 3C Homes set precedence?
Trending Topics

Will NCLT’s approval of Ace Infracity resolution plan for 3C Homes set precedence?

Legal experts say that are of the view that the order will pave the way for other projects that are stuck because of disputes with governing bodies

July 15, 2023 / 11:16 IST
Story continues below Advertisement
Under the resolution plan, allottees will get possession of 512 residential plots of the Lotus City project, valued at Rs 211 crore after it is developed

In an order that will bring relief to over 500 plot owners of Lotus City that was launched by the beleaguered 3Cs Group along the Yamuna Expressway almost a decade ago, the National Company Law Tribunal (NCLT) has approved the resolution plan submitted by Ace Infracity Developers Private Ltd. The NCLT did not entertain the objections put forward by the Yamuna Expressway Industrial Development Authority (YEIDA), the land allotting body, and held that the amount of Rs 67 crore being brought in by the corporate debtor was sufficient for them to settle their dues.

Under the resolution plan, allottees will get possession of 512 residential plots of the Lotus City project, valued at Rs 211 crore after it is developed. The term of this plan is 24 months within which the plots would be developed and delivered.

Story continues below Advertisement

Legal experts say that the order will not only bring relief to hundreds of families of this project but also clear the way for similar projects that are stuck due to disagreements with development authorities.

The NCLT bench observed the resolution plan submitted by Ace Infracity Developers has been approved by the committee of creditors (CoC) with 100 percent votes and it cannot "interfere with the commercial wisdom" of the lenders.