Noida Twin Towers Demolition: Edifice expedites work to complete charging of Apex with explosives by August 23

Noida Twin Towers Demolition: Edifice Engineering said that around 250-260kg of explosives are being deployed daily on average and the total quantity will be around 3700 kg.

August 18, 2022 / 14:52 IST
Story continues below Advertisement
Noida Twin Towers: Ceyan is around 97 metres tall while Apex is 100-metre high. (Photo: Moneycontrol)
Noida Twin Towers: Ceyan is around 97 metres tall while Apex is 100-metre high. (Photo: Moneycontrol)

Edifice Engineering, the company hired by Supertech to carry out the demolition of the Twin Towers located in Noida Sector 93A, completed the charging of one of the towers on August 17 and now has shifted its focus on Apex tower to complete its charging by August 22 or 23. The firm had earlier set a target to complete the charging by August 25. Charging is a process to fill the holes drilled in columns of the towers with explosives. Edifice Engineering is carrying out the demolition with South Africa-based Jet Demolition.

"We completed charging of Ceyane, which has 29 floors, yesterday (August 17). We finished charging the 24th and 22nd floors of Apex (32 floors) yesterday and we are working on floors 20th, 18th and 16th today (August 18). We are trying to complete the charging of Apex by August 22-23 as we need three to four days for the final connection and checking. In the final connection, explosives on all the floors will be interconnected so that the blast can be carried out simultaneously," said Mayur Mehta, project manager at Edifice.

Story continues below Advertisement

Also Read: Buyers in Supertech’s Twin Tower in Noida await refunds

Mehta shared that around 250-260 kg of explosives are being deployed daily on average and the total quantity will be around 3700 kg.