HomeNewsBusinessMarketsNTPC hits 52-week high as Barh plant completes trial

NTPC hits 52-week high as Barh plant completes trial

In the first quarter of FY24, the production from NTPC's captive coal mines nearly doubled to 8.48 million metric tonnes (MMT).

July 07, 2023 / 11:13 IST
Story continues below Advertisement
With this, the installed capacity of NTPC Limited and NTPC group has become 57038 MW and 73024 MW respectively, the company said.
With this, the installed capacity of NTPC Limited and NTPC group has become 57038 MW and 73024 MW respectively, the company said.

National Thermal Power Corporation (NTPC) shares gained 0.3 percent in early trade on July 07 to hit a 52-week high of Rs 197.40 apiece after the company said it had successfully completed the trial operation of Barh Super Thermal Power Project in Bihar.

The stock has gained 10.7 percent in the last one month.

Story continues below Advertisement

The completion gains significance as the plant will consequently be included in the installed capacity of NTPC Limited. "With this, the installed capacity of NTPC Limited and NTPC group has become 57038 MW and 73024 MW respectively", the company said in a disclosure to the exchanges.

In the first quarter of FY24, the production from NTPC's captive coal mines witnessed a significant increase, reaching 8.48 million metric tonnes (MMT), nearly doubling its output as compared to the first quarter of FY23 when it produced 4.27 MMT of coal from its captive mines.