HomeNewsBusinessConstruction of Delhi airport's 2nd CAT IIIB runway airstrip to be completed this week: Aviation Minister

Construction of Delhi airport's 2nd CAT IIIB runway airstrip to be completed this week: Aviation Minister

Delhi airport is targeting to complete all the activities related to runway maintenance by January 19 for Directorate General of Civil Aviation (DGCA) inspection, GMR Airport said in a letter to the Ministry of Civil Aviation (MoCA) on January 16.

January 17, 2024 / 17:07 IST
Story continues below Advertisement
Delhi Airport has informed the aviation ministry that the runway would be functional by January 26.
Delhi Airport has informed the aviation ministry that the runway would be functional by January 26.

Civil Aviation Minister Jyotiraditya Scindia said on January 17 that the rehabilitation construction project of Delhi Airport's, CAT IIIB-compliant, airstrip 28/10 would be completed this week.

Delhi airport is targeting to complete all the activities related to runway maintenance by January 19 for Directorate General of Civil Aviation (DGCA) inspection, GMR Airport said in a letter to the Ministry of Civil Aviation (MoCA) on January 16.

Story continues below Advertisement

The maintenance of the runway was expected to be completed by December 15 but pollution and enforcement of GRAP-IV in Delhi resulted in delays, said the minister.

“…the maintenance was taken on top priority to be completed by 15th December before the onset of the fog season. However, due to pollution incidents and enforcement of GRAP-IV in Delhi, the recarpeting got delayed, resulting in a delay of one month in its commissioning. The revamped RWY is getting operational this week,” said Scindia in a tweet.
Delhi Airport has informed the aviation ministry that the runway would be functional by January 26.