HomeNewsIndiaOver 75% of 37 bridges, 97.6% tunnelling work on Katra-Banihal railway link completed: Officials

Over 75% of 37 bridges, 97.6% tunnelling work on Katra-Banihal railway link completed: Officials

The Katra-Banihal stretch is part of the prestigious Udhampur-Srinagar-Baramulla Rail Link (USBRL) Project which has missed several deadlines in the past amid huge cost escalations since 1997.

August 16, 2022 / 16:30 IST
Story continues below Advertisement

More than 75 per cent of the total 37 bridges and 97.6 per cent tunnelling work on the vital Katra-Banihal railway link stands completed, officials of the northern railways said, expressing hope that Kashmir will be connected to rest of the country via train next year.

The Katra-Banihal stretch is part of the prestigious Udhampur-Srinagar-Baramulla Rail Link (USBRL) Project which has missed several deadlines in the past amid huge cost escalations since 1997, when the then Prime Minister H D Deve Gowda laid its foundation at Udhampur.

Story continues below Advertisement

In view of the importance of the USBRL project in providing seamless and hassle-free connectivity, the 272-Km-long railway line project was declared as a 'national project' in 2002. While the 161 km was commissioned in phases with first phase 118-km Qazigund-Baramulla section commissioned in October 2009 followed by 18-km Banihal-Qazigund in June 2013 and 25-km Udhampur-Katra in July 2014.

"The intervening stretch of the Katra-Banihal section (111 km) is in progress. This is, perhaps, the most difficult new railway line project undertaken in the Indian subcontinent. This section predominantly involves tunnelling of 164 Km (97.57 km main tunnel and 66.4 km of escape tunnel), in addition to construction of 37 bridges on Chenab river and its tributary Anji Khad," an official said. At present, he said 160.52 Km of tunnelling (95.47 km of main tunnel and 65.05 km of escape tunnel) and 28 bridges, out of total 37 have been completed, the official said.