HomeNewsBusinessSikkim flash flood | Power ministry investigating early warning system at Teesta Urja hydropower project: RK Singh

Sikkim flash flood | Power ministry investigating early warning system at Teesta Urja hydropower project: RK Singh

Calling the GLOF calamity a "freak incident", the Union minister for power said the Indian government is not ready to write off hydropower projects as yet.

October 18, 2023 / 19:58 IST
Story continues below Advertisement
Sikkim
Sikkim flash floods

Two weeks after a Glacial Lake Outburst Flood (GLOF) in North Sikkim washed away the Chungthang dam of the 1,200 MW Teesta Stage-III hydropower plant, Union Minister for Power RK Singh said on October 18 that his ministry is looking into the early warning system of the hydropower project concerned.

Moneycontrol on October 12 reported that the government's plan to install early warning systems in vulnerable hydro projects remains incomplete despite it roping in the Defence Research and Development Organisation (DRDO) in December 2022.

Story continues below Advertisement

"We had put in place early warning mechanisms for hydropower projects so that one knows when there is an upcoming flood and they can open the gates accordingly. In the case of the Chungthang dam, either an early warning system was not installed at all or it was not functional at the time of the incident. We are looking into this," the minister said on the sidelines of an event organised by the International Solar Alliance (ISA).

The Teesta Stage-III plant is commonly known as the Teesta Urja project.