The builder should also pay the compensation and litigation cost to the homebuyers who had sought refund of the amount, rules the apex commission

July 08, 2019 / 13:54 IST
Story continues below Advertisement

Coming down heavily on a real estate developer for ‘deficiency in service’ and ‘unfair trade practice’ and not handing over housing units within the stipulated time frame, the National Consumer Disputes Redressal Commission has ordered that the builder refund the money for the delayed project with interest, and pay the compensation and litigation cost to homebuyers who had sought a refund.

‘…we find, both, deficiency in service within the meaning of section 2(1)(g) & (o), and unfair trade practice within the meaning of section 2(1)(r), to be well and truly evident on the part of the builder co,” the order said.

Story continues below Advertisement

‘In remedy, it is appropriate to direct the builder company to refund the principal amount deposited by the complainant with the builder co., with just and equitable interest, a lumpsum compensation, and cost of litigation, to the complainant,’ it said.

The commission was hearing the plea of 20 homebuyers who had invested Rs 10 crore in 2012 in Wave Garden housing project located in Mohali. Despite promising to deliver the units within three years, the developer had failed to complete construction even after seven years.