Green clearance delays may push construction of new Delhi metro line to 2025

The Delhi Forest Department has asked for the project to be modified so that fewer trees are cut down. Accordingly, the DMRC is now looking to re-align the metro towers.

August 26, 2024 / 07:21 IST
Story continues below Advertisement
The Lajpat Nagar to Saket G Block corridor is being established to provide hassle-free connectivity to areas including Andrews Ganj, Greater Kailash 1, Chirag Dilli, Pushpa Bhawan, Pushp Vihar, Saket District Centre and Saket G Block.

Construction of  the Delhi Metro Rail Corporation’s (DMRC’s)  new brown line, connecting Lajpat Nagar to Saket G block may not  start in late 2024 as planned as the DMRC is yet to obtain forest clearances and permission for cutting trees, multiple sources aware of the ongoing discussions told Moneycontrol.

Construction  of the new corridor, under phase 4, is expected to start in 2025 now.

Story continues below Advertisement

"Work on the new metro line will start in the first half of 2025 as the detailed project report (DPR)  is delayed because getting forest clearances and permission to cut trees  is taking time," a senior DMRC official told Moneycontrol.

He added that the Delhi Forest Department has requested that the DPR be modified so that fewer trees may be chopped down in Hauz Khas forest and Jahanpanah city forest.