First batch of Metro trains for Bengaluru’s Electronics City to be shipped from China on October 18: Titagarh

Electronics City Metro corridor to miss December 2023 deadline; Titagarh to supply trains from February 2024

October 05, 2023 / 11:52 IST
Story continues below Advertisement
The first two Metro trains from China Railway Rolling Stock Corporation (CRRC) will depart from China on October 18 and are expected to arrive in Bengaluru within a month
The first two Metro trains from China Railway Rolling Stock Corporation (CRRC) will depart from China on October 18 and are expected to arrive in Bengaluru within a month

While civil work on Bengaluru Metro’s Yellow Line (RV Road-Bommasandra) is nearing completion, uncertainty looms over the arrival of rolling stock, keeping residents, officegoers, and others waiting.

“The first two Metro trains from China Railway Rolling Stock Corporation (CRRC) will depart from China on October 18 and are expected to arrive in Bengaluru within a month.” Prithish Chowdhary, director of marketing and business development, Titagarh Rail Systems, told Moneycontrol.

Story continues below Advertisement

In addition, two car bodies for Metro trains manufactured by CRRC are currently en route from China to Titagarh’s production facility in Uttarpara near Kolkata and will arrive in the next two weeks.

“Once the two car bodies from CRRC reach our production facility, we will commence work on them and supply the trains to Bangalore Metro Rail Corporation Ltd (BMRCL) by February 2024,” Chowdhary said.