HomeNewsBusinessAdani Power's 1,600 MW Godda thermal power plant becomes fully operational

Adani Power's 1,600 MW Godda thermal power plant becomes fully operational

APJL will supply 1,496 MW net capacity power from the 1,600 MW Godda USCTPP under the power purchase agreement (PPA) with Bangladesh Power Development Board (BPDB)

June 27, 2023 / 20:18 IST
Story continues below Advertisement
Adani Power
Adani Power

Adani Power on June 27 said that it has started commercial operations of the second and last unit of 800 megawatts (MW) at its ultra-supercritical thermal power plant (USCTPP) in Jharkhand's Godda district.

With this, the Godda USCTPP has become fully operational and the electricity generated from the plant is being supplied to Bangladesh as per the contracts, the company said in a statement on June 27.

Story continues below Advertisement

Adani Power's Godda USCTPP has a total capacity of 1,600 MW with two units of 800 MW each. On April 6, the first unit of the power plant, with 800 MW capacity, achieved its commercial operations date (COD).

"Adani Power Jharkhand Limited (APJL), a wholly owned subsidiary of Adani Power Limited, part of the diversified Adani Group has achieved COD of its second unit of the Godda USCTPP on June 26 2023.