HomeNewsIndiaNew Parliament building to be completed by October 2022, Central Vista Avenue by November this year: Government

New Parliament building to be completed by October 2022, Central Vista Avenue by November this year: Government

The government has also said that environment clearance has been obtained from the Environment Ministry on May 31, 2021

July 22, 2021 / 13:47 IST
Story continues below Advertisement
Architectural rendering of the new Parliament building, proposed to be built as part of the Central Vista project. (Image courtesy: Twitter/@LokSabhaSectt)
Architectural rendering of the new Parliament building, proposed to be built as part of the Central Vista project. (Image courtesy: Twitter/@LokSabhaSectt)

The New Parliament building is targeted to be completed by October 2022, in the 75th year of Indian Independence, and the development of the Central Vista Avenue will be complete by this November, the government has told the Parliament on Thursday.

The government has also said that environment clearance has been obtained from the Environment Ministry on May 31, 2021, for other projects as part of the development of the Central Vista Master Plan, which includes Common Central Secretariat Buildings and Central Conference Centre, Prime Minister’s Residence, Special Protection Group (SPG) Building and Vice President’s Enclave.

Story continues below Advertisement

Environment Clearance (EC) for the New Parliament Building was granted by the Ministry of Environment on June 17 last year.

“None of the listed heritage buildings will be demolished under the Central Vista Development Master Plan. All the materials in National Archives and National Museum would be available to scholars and researchers during the construction,” the government has further told Parliament.