Strategic Leh-Kaithal Green Energy Corridor gets President's assent

PGCIL is likely to place all orders for the project by March 2025 and it is likely to be a reality by FY2030

February 22, 2024 / 16:25 IST
Story continues below Advertisement
The project is a major step toward India's target of achieving 500 GW of installed electricity capacity from non-fossil fuels by 2030

The President of India has cleared the construction of India’s ambitious Green Energy Corridor (GEC) for evacuation of 13GW renewable energy from Ladakh.

The President has approved a Central Financial Assistance of Rs 8,309.48 crore for the strategic project which will be built at an estimated cost of Rs 20,773.70 crore. The approval came on February 15 as per the letter sent by the Ministry of New and Renewable Energy (MNRE).

Story continues below Advertisement

The transmission line for evacuating green power from the under-construction renewable energy park in Ladakh will start from Pang (Ladakh) and will pass through Himachal Pradesh and Punjab, after which it will end in Kaithal in Haryana, where it will be integrated with the national grid.

It was on October 18, 2023, when the project received its final approval from the Cabinet Committee on Economic Affairs, chaired by Prime Minister Narendra Modi.