UP RERA grants more time to promoter to complete Ghaziabad housing project

The promoter had already availed of the entire permissible extension of registration, one year as per section 6 of RERA Act and other extension due to Covid-19

July 25, 2022 / 23:04 IST
Story continues below Advertisement
Presently, as per the site inspection report, the overall physical progress of the project is only 40 per cent," U.P. RERA said in a statement.

The Uttar Pradesh Real Estate Regulatory Authority (RERA) has permitted the promoter of a Ghaziabad-based project to complete the remaining development and construction work by December 2023.

The Authority noted that the project - Utopia Estate - commenced in April 2016 but could not be completed by the promoter Sai Adhiraj Land & Promoters Pvt. Ltd. within the period of registration i.e, March 28, 2022.

Story continues below Advertisement

"Presently, as per the site inspection report, the overall physical progress of the project is only 40 percent," U.P. RERA said in a statement.

It noted that both the promoter and the association of allottees had approached U.P. RERA to intervene in the matter and facilitate the remaining development work of the project.