Rs 419.55 crore spent so far on work undertaken under Central Vista Master Plan

The new Parliament building project, which has its deadline in October, has achieved 44 percent physical progress, and the government has so far spent Rs 480 crore on it, the Rajya Sabha was informed on March 21

March 21, 2022 / 20:49 IST
Story continues below Advertisement
The work on the project has continued despite the lockdown in the national capital that has brought most construction sites to a grinding halt. The construction work for the project has been brought under the ambit of "essential services", a move that been flayed by the Opposition. (Image: Twitter/@HardeepSPuri)

The government has so far spent Rs 419.55 crore on the work undertaken under the Central Vista Master Plan, the Rajya Sabha was informed on March 21.

The housing and urban affairs ministry provided the status and progress of ongoing work under Central Vista Master Plan and said that Rs 1423 crore will be the likely expenditure on the entire Central Vista project in 2021-2022 and Rs 2285 crore in 2022-2023.

Story continues below Advertisement

This information was shared by Minister of State for Housing and Urban Affairs Kaushal Kishore in a written reply.

He said that the ministry along with the CPWD was monitoring all the Central Vista projects on a weekly basis to avoid delays.