NCDRC order that builders cannot cite excuses for delay in delivery to have pan-India impact

Most common excuses given by real estate developers range from hurdles in land acquisition, labour issues, restrictions on extraction of ground water, NGT orders

December 18, 2018 / 10:02 IST
Story continues below Advertisement

Vandana Ramnani Moneycontrol News

In its recent order, the apex consumer commission - National Consumer Disputes Redressal Commission (NCDRC) - has ruled that a real estate developer cannot cite excuses such as delay in approvals by authorities, issues of land acquisition to justify late delivery of projects.

This order, say real estate and legal experts, is expected to have repercussions on most projects located across the country.

Story continues below Advertisement

The bench directed a subsidiary of real estate major DLF to hand over possession to 16 homebuyers who have booked units in Panchkula in Haryana.

It directed the company to pay compensation of Rs 1 lakh per annum as delay and interest on the amounts paid by homebuyers and ordered the builder to complete the process of getting the sale deeds registered.