HomeNewsBusinessReal EstateKolkata homebuyers had to wait longest for flats between 2014 and 2024: Anarock

Kolkata homebuyers had to wait longest for flats between 2014 and 2024: Anarock

Homebuyers had to wait less for their homes to be completed between 2014 and H1 2024, than they did between 2010 to 2019. Kolkata, however, lagged behind other major markets in that metric

July 16, 2024 / 12:04 IST
Story continues below Advertisement
In major markets such as the Mumbai metropolitan region, the construction timeline between 2014 and June 2024 declined to 5.2 years, against 6.5 years in projects between 2010 and 2019, according to Anarock
In major markets such as the Mumbai metropolitan region, the construction timeline between 2014 and June 2024 declined to 5.2 years, against 6.5 years in projects between 2010 and 2019, according to Anarock

The time difference between launch and completion of residential projects between 2014 and June 2024 has reduced by around 20 percent to 4.9 years across seven major housing markets, compared to projects that began between 2010 and 2019, according to a report.

However, even after a 10 percent drop in time taken, properties launched in Kolkata between 2014 and Jan-June 2024 saw an average of 5.7 years for project completion, a report from the real estate consultancy Anarock showed.

Story continues below Advertisement

The launch-to-completion timeline for housing projects between 2010 and 2019 was 6.1 years across the top seven markets, which includes the Mumbai metropolitan region, National Capital Region, Chennai, Kolkata, Bengaluru, Pune, and Hyderabad, the report added. The same for Kolkata, during that period, was at 6.3 years.

In major markets such as the Mumbai metropolitan region, the construction timeline from 2014 to Jan-June 2024 declined to 5.2 years, against 6.5 years in projects from 2010 to 2019, according to the report. For the National Capital Region, which had been beset with issues such as errant and financially insolvent developers, the construction timeline was down to 5.4 years for projects launched between 2014 and first half of 2024 , compared to 7.2 years in the 2010-2019 period.