HomeNewsBusinessReal EstateFlat delayed by four years, NCDRC tells builder to refund homebuyer Rs 3.4 crore with interest

Flat delayed by four years, NCDRC tells builder to refund homebuyer Rs 3.4 crore with interest

The consumer court also said the terms of the agreement signed between the two parties were wholly one-sided and unfair to the homebuyer.

July 27, 2020 / 13:53 IST
Story continues below Advertisement

The country's top consumer court has directed Gurugram-based Pioneer Urban Land & Infrastructure Ltd to refund the entire principal amount of Rs 3.45 crore with interest and Rs 25,000 as litigation cost to a homebuyer for a four-year delay in handing over of an apartment.

The National Consumer Disputes Redressal Commission (NCDRC) also held as wholly one-sided and unfair the terms of an “apartment buyer’s agreement” signed between the two sides. The court overlooked the developer’s argument that the delay was because of circumstances that were out of its control.

Story continues below Advertisement

“The interest at 9 percent per annum has been awarded in the light of the observation of the honourable Supreme Court in a catena of judgments awarding interest, keeping in view the current market situation and that the banks have lowered the interest rates,” the order dated July 23 said.

In view of the disruption caused by the coroanvirus outbreak, the court gave the developer three months to comply with the order, failing interest rate will be raised to 12 percent.