HomeNewsBusinessHimachal floods delayed Parbati-II hydropower project commissioning to FY25

Himachal floods delayed Parbati-II hydropower project commissioning to FY25

NHPC Ltd CMD RK Vishnoi also said that the first and second units of the Subansiri Lower hydroelectric project in Arunachal Pradesh will be commissioned in January and March, 2024 respectively.

September 01, 2023 / 17:55 IST
Story continues below Advertisement
NHPC Ltd
NHPC has a 15 percent share (6,971 MW) of the total installed hydro-electric capacity of 46,850 MW.

The commissioning of the Parbati-II hydropower project, which was delayed by about 13 years due to tunnelling issues, has slipped further into FY25, according to NHPC Ltd.

NHPC Ltd, India's largest state-owned hydropower company, had initially planned to commission the 800 MW project in Himachal Pradesh's Kullu district in March 2024. The plant consists of four units, each with a capacity of 200 MW.

Story continues below Advertisement

However, recent heavy rains and floods in Himachal Pradesh have significantly impacted the hydropower plant's supporting infrastructure, including access routes and approaches, resulting in additional delays.

"We had originally intended to commission two units in this financial year (FY24). However, the rains and floods in Himachal Pradesh have been a setback, particularly for this project. As a result, these two units will now be commissioned in early FY25," said Rajeev Kumar Vishnoi, the Chairperson and Managing Director (CMD) of NHPC Ltd during a recent interaction with investors.